CEA Prevents Costly Delays and Secures Long-Term Performance for Sonnedix
Summary
On-site commissioning oversight ensures long-term solar performance
Sonnedix, an international renewable energy producer, engaged Clean Energy Associates (CEA) to conduct commissioning inspections for its newly installed solar projects. CEA provided independent verification that work met stringent quality and safety standards and took a proactive approach to identify and resolve issues early, preventing delays, avoiding rework, and safeguarding long-term performance.
The Challenge
As Sonnedix prepared to commission new solar assets, it needed to ensure its EPC partner delivered work to scope and quality standards. Lapses in documentation, testing, or imaging could cause costly rework, delays, and long-term performance issues—especially in large or remote installations.
The Solution
CEA served as an independent technical advisor, verifying commissioning quality through documentation reviews, on-site inspections, and technical analysis. CEA:
Monitored testing procedures in real time
Improved IR imaging accuracy
Identified and flagged deviations early
Worked closely with Sonnedix and the EPC to align outcomes
“It has been a pleasure to collaborate as a team. CEA personnel have been very supportive and proactive in the project.”
The Result
CEA's oversight ensured a smooth, high-quality commissioning process while reducing risk and cost. Key outcomes included:
Quality Assurance: Verified inspections and EPC compliance
Risk Mitigation: Caught test and imaging issues early
Cost Savings: Reduced rework and financial exposure
Efficient Delivery: Coordinated punch list and test completion
Performance Assurance: Improved imaging and testing to support long-term reliability
CEA's early intervention prevented delays and rework, enabling Sonnedix to avoid cost overruns and confidently expand its project portfolio through 2027.